Scheduling Diagrams

Scheduling Diagrams
  • The process of assigning workers to tasks is known as scheduling.
  • It is important to know how to construct a scheduling diagram, to show which workers should be assigned to which activities.
  • When you are scheduling an activity, you should always use the first avaliable worker and if there is a choice of activities for a worker, assign the one with the lowest late time value.
Example 1

Question 1
  1. \(22 \times 3=66\)
    -Project time is\(64\)
    \(\therefore\) lower bound should be 3 workers
  2. B has a float of 3, therefore a delay of 2 hours should not change the overall planning structure.
  3. J and H must be happening at 17.5 hours into the project