Resource Histograms

Resource Histograms use case
  • Resource Histograms are used to consider how may workers are needed to carry out a particular task
    Rules
    • No worker can carry out more than one task simultanously
    • Once a worker, or workers, have started an activity, they must finish it.
    • Once a worker, or workers, have finished a task, they immediatly become avaliable to start another activity.
  • The histogram shows how many workers are active at any given time.
  • One way to draw a resource histogram is to start with a Gantt Chart.
Drawing resource histograms
Example Question





Question 1