Modelling a Project

The Dinner Date

Activities

Shower/Prep: 10 mins
Setting Table: 15 mins
Dumplings Prep: 30 mins
Dumplings Cook: 10 mins (100%)
Noodles Prep: 5 mins
Noodles Cook: 15 mins
Brownies Prep: 10 mins
Brownies Cook: 25 mins

Brownies Prep + Brownies Cook + Shower/Prep + Setting the table + Dumplings Prep + Dumplings Cook + Noodles Prep + Noodles Cook

30+10+5+10+25=1.20

Presedence Tables

Presedence Tables
  • Presedence Tables can be used to show which activities must be completed before another activity starts.
  • When another activitiy cannot start until another activity is completed it is called a dependency

    700x500
    700x500

Activity networks

Info
  • On Activity Networks (also called arc networks), the arcs are referred to as activities, and the nodes represent the completion of the task.
  • Each arc/task is labelled with a letter to represent it and the arrow is used to define the direction. The nodes are numbered starting from 0 (or 1).
  • The first node is called the source node.
  • You have to number each node as it is added to the network.
  • The final node is called the sink node.


    YOU CANNOT HAVE TWO ACTIVITIES WITH THE SAME START/FINISH NODE